How long window installation takes depends on two separate clocks: the hours a crew spends fitting windows on site, and the weeks between placing the order and the fitting date. As a rough typical guide, a standard window takes about one to three hours to fit, a typical three-bedroom semi-detached house is usually finished in one to three days, and the wait from order to fitting commonly runs from four to six weeks for standard sizes, rising to six to ten weeks for made-to-measure units and longer for shaped ones. Anyone arranging a window and door installation should plan around both periods, because the ordering stage is normally the longer of the two.
Fitting time on site versus the wait for the order
The fitting stage is short and visible: the old unit comes out, the opening is prepared, the new frame is set, levelled, packed, fixed and sealed, the trims go back on and the crew moves to the next opening. The lead time is invisible but usually longer, covering a survey, manufacture of the frames and glazing, delivery, and a slot in the fitting crew's diary.
Typical order-to-fitting lead times:
- Standard casement or tilt-and-turn windows in common sizes and colours: about four to six weeks.
- Made-to-measure sizes, non-standard colours, triple glazing, timber or aluminium-clad frames: about six to ten weeks.
- Arched, angled or very large units, or a whole house ordered in the busiest spring period: eight to twelve weeks.
These are typical figures rather than fixed rules. A local order can come forward if there is a cancellation, and a bespoke one can slip if a component is delayed. The practical point is that the diary note belongs on the order date, not on the day the crew arrives.

How long fitting takes per window
The table below is a typical guide for a two-person crew working on a straightforward opening with reasonable access.
| Window or door type | Typical on-site fitting time |
|---|---|
| Small fixed or top-hung window | 1 to 1.5 hours |
| Standard casement window | 1 to 3 hours |
| Large or triple-glazed window | 2 to 4 hours |
| Bay, corner or arched window | 3 to 6 hours |
| Patio or French door | 2 to 4 hours |
| Composite or timber entrance door | 2 to 4 hours |
Removing an old window usually adds 20 to 45 minutes per opening, and making good the internal reveal adds roughly another 20 to 45 minutes spread across the job. A working day for most crews covers five to eight openings, fewer in midwinter or where access is awkward.

How long a whole house takes
Whole-house times depend on the number of openings, the number of floors and how complex the units are.
- A three-bedroom semi-detached house with eight to twelve openings: one to three days on site.
- A larger detached house with twelve to twenty openings: two to four days.
- A dormer bungalow or a house where upper-floor windows need a tower or scaffold: three to five days.
- A house with several bays, arched units or full-height glazing: five days or more, often split over two visits.
A second crew working at the same time can shorten the on-site time considerably where parking and access allow. Internal finishing, such as patching plaster or painting around reveals, is often left to a later day or to a separate tradesperson, which is why a house can still feel unfinished a week after the windows are in.
What makes a job take longer
Access and upper floors
Ground-floor windows are the quickest, because tools, frames and materials can be kept close by. Anything above the first floor usually means a tower, a platform or scaffolding, and that equipment has to be delivered, erected and removed. Roughly an extra half day to a full day is typical where scaffolding is needed across the front and back of a house.
Condition of the openings
Sound plaster and straight, square openings are the fastest to work with. Crumbling reveals, rotten timbers, damaged lintels, uneven blockwork or a frame that has been rendered over can each add an hour or more per opening. Where the size of the opening has to change, a builder is normally brought in and the work grows into a longer project.
Frame material and glazing type
Standard uPVC casements with double glazing are the lightest and quickest to handle. Timber and aluminium-clad frames are heavier and often need more careful packing and fixing, and triple-glazed units weigh more again, so a larger window may need a third pair of hands or a lifting aid.
Custom sizes and shapes
Non-standard widths, full-height units and shaped frames take longer to make and longer to fit. Anything beyond a straightforward rectangle should be expected to add to the lead time as well as to the hours on site.
Weather and time of year
External sealant and expanding foam need a reasonably dry surface, so heavy rain can push the external sealing of a window to a later visit even after the frame is in. High wind is the bigger obstacle at height and can stop upper-floor work for the day. Winter also shortens the working day, so a crew that fits seven windows in June may fit four or five in December.
Removal and disposal of the old windows
Old timber sash windows with weights and pulleys, or frames bedded into concrete, take longer to free than a screw-fixed uPVC unit. The old frames and glass then have to be carried out, loaded and taken away, and that handling is part of the day's work even though it produces no visible result.
Making good and finishing
Internal sealant, trims, plaster patching and paint touch-ups come last and are what homeowners notice most afterwards. Rushing them is the main reason a fast job looks untidy a year later, so an extra half day at the end is usually worth accepting.
Where windows are one part of a bigger construction and home renovation project, the fitting slot also has to be sequenced around blockwork, rendering and plastering, and that coordination, rather than the fitting itself, is what stretches the overall schedule.



